Space Juggling Team
Timeline
- January 31 - T-minus 18 days to complete light rig + stars
- Feb 15 - Costume done / Cables & Webbing completed
- Feb 19 - Adam filming solo with costume and all lighting
- Feb 26 - Adam filming solo with costume and all lighting
- March 19 (weekend) - cinematic intro/outro
- March 26 (weekend) - cinematic intro-outro
- April 2 Friday - All footage to Jeremy / First Draft of Music Due
- April 5 Monday - First rough cut (rough pasting of clips for framework - overall feel, no motion graphics, no coloring, framework, no music ---> music)
- April 8 Thursday - Second Cut (clip selection, music start finalizing) / Final Draft of Music Due
- April 10 Saturday - Third Cut (clip selection almost final, rough motion graphics, music)
- April 12 Monday - First full draft (locking in frames for motion graphics, final color, music)
- April 19 - Video out the door
- April 12 - (still Yuri’s Night)